Contractor field guide · Two free templates

Authorize the rates. Record the day.

Use an advance T&M authorization to set the rules, then a daily field ticket to preserve labor, materials, equipment, receipts, progress, and the running total.

  • 14 minute read
  • Updated July 10, 2026
  • Variable-scope work
A contractor reviews a daily time-and-materials ticket with receipts and a progress photo.
Daily record 01 Match labor, receipts, and progress evidence at the end of each shift.

The short answer

Authorization and daily documentation are different jobs.

The authorization defines scope, labor rates, materials and equipment treatment, markup, tax, estimate, ceiling, payment, schedule, and permission to proceed. The daily ticket records actual resources and progress under those rules.

An estimate predicts. A not-to-exceed amount limits. Do not use the terms interchangeably.

T&M control loop

Set rules once. Close records daily.

  1. 01

    Define the variable scope

    Identify authorized tasks, location, exclusions, and the condition that makes final effort uncertain.

  2. 02

    Set every rate and cost rule

    List labor categories, materials, equipment, travel, overtime, markup, tax, minimums, and subcontract treatment.

  3. 03

    Estimate and cap

    Separate the good-faith estimate from an explicit not-to-exceed ceiling and notification threshold.

  4. 04

    Record each day

    Capture time, receipts, equipment, progress, photos, daily total, cumulative total, and remaining ceiling.

  5. 05

    Reconcile and retain

    Correct discrepancies promptly, define acknowledgement meaning, and preserve all tickets with the agreement.

Template 01

T&M work authorization

Establish the billing rules before variable work begins. Use a compliant underlying agreement for the project and jurisdiction.

Create and sign it with JobSign →
Authorization no. [___]Pricing rules
Project & scope boundary
[Customer, property, work area, original agreement, authorized tasks, exclusions, stop conditions]
Labor categories & rates
[Technician $___/hr; helper $___/hr; specialist $___/hr; minimums, travel, overtime, and rate inclusions]
Materials
[Actual documented cost / stated basis; markup ___%; freight, consumables, returns, discounts, and tax]
Equipment & other costs
[Item, rate/basis, operating or standby time, rental, disposal, permit, and subcontract work]
Estimate
Labor $___ + materials $___ + equipment/other $___ = estimated $___; not a ceiling unless expressly stated
Not-to-exceed / stop point
[Do not exceed $___ or ___ hours without approval; notify customer at $___]
Records & review
[Daily tickets, time entries, receipts, invoices, photos, measurements, and review timing]
Payment & schedule
[Daily/weekly/completion billing, payment due, start date, anticipated duration, completion effect]
Customer / authorized representativeSignature & date
ContractorSignature & date

Pricing and disclosure rules vary. Do not use an informal T&M ticket to bypass required contract terms, notices, dates, or payment schedules.

Template 02

Daily T&M field ticket

Complete it on the work date. Use a dated clarification for corrections rather than silently replacing the original field record.

Ticket date [___]Daily record
Authorization & location
[Authorization/change order number, property, room/area, work date, ticket number]
Work performed
[Specific tasks, condition encountered, quantity/progress, remaining work, and off-site work]
Labor
[Worker/category | start | stop | breaks | billable hours | rate | amount]
Materials
[Item | quantity | receipt/invoice | cost basis | markup/tax | amount | return/credit]
Equipment & other
[Item | operating/standby hours | rate | amount | disposal/rental/subcontract reference]
Daily total
Labor $___ + materials $___ + equipment/other $___ + applicable tax $___ = $___
Cumulative & ceiling
Prior $___ + today $___ = $___ of $___ ceiling; remaining $___
Evidence
[Before/progress/after photos, measurements, receipts, delivery/haul tickets, issue notes]
Acknowledgement meaning
[Confirms observed record only / authorizes billing / other expressly stated effect]
Customer / site representativeAcknowledgement & date
Contractor forepersonSignature & date

Completed example

Plumbing diagnosis and access repair

Labor

Technician 4.0 hours

Diagnosis, limited access, fitting replacement, test, and temporary closure at the agreed rate.

Materials

Fitting and supplies

Receipt attached; unused fittings returned; material markup shown separately.

Evidence

Five progress photos

Before condition, access boundary, failed fitting, completed connection, and test result.

Ceiling

Total below NTE

Daily and cumulative totals shown; permanent finish restoration remains excluded.

Daily checklist

Close the record while the day is fresh.

Time

Start, stop, breaks

Record actual time by category and separate nonbillable work.

Cost

Receipts and returns

Attach evidence and account for unused or credited items.

Progress

Work accomplished

Connect resources to authorized scope with location, quantity, and photos.

Limit

Running ceiling

Show cumulative cost and stop before exceeding authorization.

Research basis

T&M needs defined rates, records, and active controls.

FAR 16.601 describes T&M as labor hours at specified fixed hourly rates plus material cost and warns that this structure offers no positive incentive for cost control, making oversight important. Oregon CCB describes homeowner T&M as hours billed, materials used, and agreed markup, and warns an estimate may be exceeded without a not-to-exceed clause.

Caltrans force-account guidance illustrates useful daily discipline: record authorized work, date, location, labor, equipment, materials, hours, quantity or progress, and supporting invoices on the day observed. These are drafting examples, not residential rules.

Time and materials questions

Is a daily ticket the same as authorization?

No. Authorization establishes the rules; the ticket documents performance under them.

Does an estimate cap the price?

No. Use explicit not-to-exceed language when a ceiling is intended.

Should material markup be included?

Only as allowed and disclosed by the agreement and applicable law. State its basis and percentage.

What does the customer signature mean?

Say whether it confirms field quantities, authorizes billing, or has another defined effect.

Authorize once. Record daily.

Keep variable work transparent from first hour to final total.

Use JobSign to set the T&M boundary, attach daily evidence, and preserve the customer record.