Document the change before the work changes.
Turn a field discovery, customer request, added item, deletion, or product change into a clear amendment that connects scope, price, payment, and schedule.

The short answer
A change order amends the original agreement.
It identifies the original contract, describes what is added, removed, or replaced, records the reason and supporting evidence, states the price and payment effects, explains schedule consequences, and captures approval before the changed work begins.
A strong change order makes three comparisons explicit: original scope versus changed scope, previous price versus revised price, and previous schedule versus revised schedule.
When to use one
Use a change order when the agreement changes.
Concealed condition
Water damage, unsuitable substrate, hidden wiring, decay, or another condition changes the required work.
Requested addition or deletion
The owner adds an outlet, removes a cabinet, changes layout, or expands the repair.
Selection or substitution
A finish, fixture, model, material, or allowance selection changes cost, labor, or timing.
Design or inspection revision
A designer, engineer, manufacturer, permit reviewer, or inspector requires changed work.
Copyable template
Contractor change order
Replace bracketed prompts. Attach marked photos, drawings, quotes, and product records rather than making the description carry every detail alone.
Create and sign it with JobSign →- Parties & project
- [Customer, contractor, property, contact details, license/reference information as applicable]
- Original agreement
- [Contract/work order date, number, original scope section, drawing, estimate, or proposal reference]
- Reason for change
- [Customer request, concealed condition, design revision, product change, inspection, quantity, or other trigger]
- Added or changed work
- [Location, quantity, dimensions, method, materials, manufacturer/model/finish, protection, disposal, and completion standard]
- Deleted work & credits
- [Exact work no longer included, committed/completed cost, material disposition, and itemized credit]
- Exclusions & stop conditions
- [Work not included, assumptions, hazardous/unsafe conditions, further discovery, and additional approval boundary]
- Price calculation
- Added work $___ − credits $___ + tax/fees/authorized adjustments $___ = net change $___
- Revised contract price
- Previous contract price $___ +/− net change $___ = $___
- Payment schedule effect
- [Deposit/progress/final milestone changed from $___ to $___; payment due event/date]
- Time effect
- [No change / add or subtract ___ calendar or working days / revised completion date ___]
- Attachments
- [Before photos, marked area, drawing, product data, supplier quote, estimate, inspection/design record]
- Authorization
- [Changed work starts only after required approval; unchanged contract terms remain in effect]
Requirements vary by project, contract, and jurisdiction. Adapt this operational template with qualified local guidance; it is not legal advice.
Completed residential example
Bathroom countertop upgrade
This fictional example shows the level of specificity that turns a generic request into an auditable decision.
- Original agreement
- Bathroom remodel proposal JS-104, dated June 2, 2026. Original scope: furnish and install laminate vanity countertop.
- Reason
- Customer requested an upgraded fabricated stone countertop after approving a physical sample.
- Changed work
- Delete laminate top. Template, fabricate, deliver, and install one 3 cm stone vanity top in approved sample finish with eased edge, one undermount sink cutout, faucet drilling, and standard installation.
- Excluded
- Cabinet modification, wall repair, plumbing beyond disconnect/reconnect, hidden-condition repair, and changes requested after fabrication approval.
- Price change
- Stone fabrication and installation $2,180 − laminate credit $620 = net addition $1,560.
- Revised price
- Previous contract $24,500 + $1,560 = $26,060.
- Payment effect
- $780 due at fabrication release; remaining $780 added to countertop-completion milestone.
- Time effect
- Add 7 calendar days for field template and fabrication. Revised target completion: July 24, 2026.
- Attachments
- Approved sample photo, slab/finish reference, edge profile, supplier quote, and vanity dimensions.
Field-to-signature workflow
One clean approval sequence.
Stop at the decision
Secure the site and avoid performing changed work before required approval.
Document the trigger
Capture condition, request, location, dimensions, and original-scope reference.
Price both directions
Itemize additions, deletions, credits, fees, and the revised contract total.
Sign and retain
Give both parties the executed record and preserve attachments with the original agreement.
Research basis
Scope, price, payment, and time belong together.
California CSLB’s contractor guidance says change orders should be written and signed before covered changed work begins and should describe scope, the amount added or subtracted, and the effect on progress payments. It also explains that change orders can remove original work.
Oregon CCB’s public sample identifies the changed product, revised contract price, changed completion date, and acceptance signatures. Federal E-SIGN law generally prevents denying a record or signature legal effect solely because it is electronic, while preserving other legal requirements and consumer-consent rules.
- California CSLB: Contracting for Success ↗
- Oregon CCB: Sample Change Order ↗
- 15 U.S.C. § 7001: Electronic Records and Signatures ↗
This guide is general operational information. It does not determine whether a particular document is sufficient, enforceable, properly signed, or compliant with licensing, notice, payment, or consumer-protection requirements.
Contractor change order questions
When should a change order be signed?
Before changed work begins when required by the agreement or applicable law. State rules vary, so check the project jurisdiction.
Can a change order reduce the price?
Yes. Itemize deleted scope and credits separately, then show the net change and revised price.
What if the final quantity is unknown?
Use a clearly defined unit price, estimated range, measurement method, evidence, and a not-to-exceed or stop point.
Can electronic signatures be used?
Often, but E-SIGN does not erase state-specific content, consent, disclosure, retention, or contract requirements.
From field note to signed amendment
Describe the change once. Send a clear approval.